Project background and history
| Project
background | milestone events | History
of sand nourishment Project background Since its extension in the 1960s the breakwater at the entrance to the Tweed River has trapped and reduced the supply of sand which normally would have been transported to southern Gold Coast beaches by wave action and near shore currents. Eventually the sand moved past the end of the breakwater and created a large, shallow sand bar at the Tweed River entrance that was hazardous to navigation. The Tweed River Entrance Sand Bypassing Project (TRESBP) has been devised by the Queensland and New South Wales Governments to overcome these problems. The joint project is being conducted in two stages. The first stage, which is now complete, involved dredging more than three million cubic metres of sand from the Tweed Bar and entrance to create a navigable channel and to nourish the southern Gold Coast beaches. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| That is, to replace sand on the
eroded beaches to bring them back to a condition similar to that which existed
before the breakwaters were extended in the 1960s. The second stage, in progress, provides for the operation of a permanent sand bypassing system. Sand that arrives at the permanent system on the southern side of the Tweed River entrance is trapped and pumped to the southern Gold Coast beaches. A contract was executed on the 22 December 1999 with McConnell Dowell Constructors (Aust.) Pty Ltd to design, construct and operate this system. This system is now in the operational phase. |
![]() Low Pressure pump station during construction. Clean water is pumped from inside the river entrance back to the Control Building. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Chronology of TRESBP milestone events
The dredges 'Port Frederick' and 'Faucon' were used for this work. These vessels placed sand in much shallower depths than was deposited near shore in Stage 1A. This created sand reserves which were moved onto Gold Coast beaches by wave action. Stage 1B also involved recovering and removing a wrecked fishing vessel 'Idaho' from near the breakwater. The 'Idaho' sank on the dangerous bar in December 1979 but became exposed during the Stage 1A works. Dredging and placement of 800,000 cubic metres began in August 1997 and finished in February 1999. A video monitoring project was used to observe beach changes at Rainbow Bay and Coolangatta beaches. [Top] |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Last updated: 28 November 2003




